Recent Accomplishments

The tables below contain a record of program and project accomplishments. The list will be updated approximately every month. Date color coding and superscripts indicate the following:
Date Annotation Key | ||
---|---|---|
BLACK | On Time as planned. | |
GREEN | Ahead of Planned. | |
RED | Later than Planned. | |
TAN ITALICS | Replanned Milestones ( Related article on nasa.gov ) |

This image points out various major hardware components of the observatory referred to in the tables to orient the reader. Credit: STSci
2021:
show/hide
Due Date | Item Accomplished | Completion Date |
---|---|---|
April 2021 | No Planned Milestones | |
March 2021 | Complete Cycle 1 General Observer Proposal Reviews | Completed 3/30/21 |
Sunshield Fold Complete | 4/6/21 | |
Launch Readiness Exercise #2 | Completed 3/8/21 | |
February 2021 | Complete Comprehensive System Test #5 | Completed 2/13/21 |
January 2021 | Complete Post Environmental Testing Sunshield Deployments | Completed 12/16/20 |
2020:
show/hide
Due Date | Item Accomplished | Completion Date |
---|---|---|
December 2020 | Complete Post Environmental Testing Spacecraft Bus Deployments | Completed 11/12/20 |
November 2020 | No Planned Milestones | |
October 2020 | Complete Observatory Environmental Testing | 10/2/20 |
September 2020 | ||
August 2020 | ||
July 2020 | ||
June 2020 | ||
May 2020 | ||
April 2020 | Deliver Science and Operations Center release 2.1 | 04/30/20 |
March 2020 | Replacement CTP & TWTA installed into Spacecraft | 02/24/20 |
Conduct fourth early commissioning exercise | 02/12/20 | |
February 2020 | Flight coupled loads analysis #2 delivered | 02/28/2020 |
Command/Telemetry Processor (CTP) replacement delivered | 01/13/2020 | |
January 2020 | Spacecraft Element level Sunshield post-environment folding complete | 01/22/2020 |
2019:
show/hide
Due Date | Item Accomplished | Completion Date |
---|---|---|
December 2019 | Replacement tunable wave traveling amplifiers (TWTAs) delivered | 11/22/19 |
November 2019 | Data Management Subsystem build 7.4 delivered | 11/25/19 |
Flight Software build 3.4 delivered | 08/30/19 | |
October 2019 | Spacecraft Element level post-environment deployments complete | 10/9/19 |
September 2019 | Install Science Payload onto Spacecraft Element | 8/23/19 |
Deliver the flight version of launch vehicle coupled loads analysis #2 and detailed assessment | Replanned to follow science payload installation (FY 20) | |
Spacecraft Element integration complete | 6/29/19 | |
Conduct contingency planning rehearsal #3 at the MOC | 9/27/19 | |
August 2019 | Complete Spacecraft Element post-launch environments and thermal vacuum testing folding | Replanned to follow science payload installation (FY 20) |
Observatory System Integration Review (Part 1) | 7/25/19 | |
Observatory System Integration Review (Part 2) | 10/19 | |
July 2019 | Received updated Cycle 1 proposals from the Guaranteed Time Observers. | 6/25/19 |
Conduct Science Operations rehearsal #5 at the MOC. | 7/12/19 | |
June 2019 | Complete Spacecraft Element post-launch environmental testing deployment. | Replanned to follow science payload installation. |
Complete the secondary mirror structure deployment driven by the Spacecraft Element. | 7/13/19 | |
May 2019 | No Milestones Planned for May. | |
April 2019 | Open thermal vacuum chamber door following testing | 5/19/19 (Feature Story) |
Conduct Wavefront Sensing rehearsal #3 at the MOC | 04/12/19 | |
March 2019 | Begin Spacecraft Element thermal vacuum test | 4/7/19 |
Deliver the flight version of launch vehicle coupled loads analysis #2 Observatory Model | 5/7/2019 | |
February 2019 | Deliver final results for SCE environmental testing | 4/5/2019 |
Conduct Early Commissioning Exercise #2 at the MOC | 03/06/19 (Government shutdown delay) | |
January 2019 | Conduct a SCE Comprehensive System Test in preparation for thermal vacuum testing | 09/26/18 |
2018:
show/hide
Due Date | Item Accomplished | Completion Date |
---|---|---|
December 2018 | Conduct Science Operations rehearsal #4 at the MOC | 12/21/18 |
Begin Spacecraft Element vibration testing | 11/15/18 | |
Complete the validation of science payload software | 10/27/18 | |
November 2018 | Complete Spacecraft Element Acoustic Test | 10/28/18 |
Deliver Observatory Science and Operations software build | 10/19/18 | |
October 2018 | Conduct Wavefront Sensing rehearsal #2 at the Missions Operations Center (MOC) | 10/6/18 |
Stow the sunshield into launch position following repairs of the membrane covers | 9/28/18 | |
Spacecraft Element (SCE) ready for resumption of environmental testing following MCA repairs | 10/19/18 | |
September 2018 | Complete integration of the Telescope onto the Spacecraft Element | Replanned to 09/2019 |
August 2018 | Complete Telescope delivery to Northrop Grumman | Replanned to 08/2019 |
Conduct Integrated Team Exercise #1 | Alternate milestone selected for 2019 ( * )
|
|
Cycle 1 General Observers proposal selection | Replanned to 07/2019 | |
Deliver Spacecraft Element to Observatory Integration and Test | Alternate milestone selected for 2019 ( * )
|
|
July 2018 | Complete Ground Segment test #2 | 7/25/18 |
Retension sunshield after thermal vacuum testing of the Spacecraft Element | Replanned to 06/2019 | |
Conduct Spacecraft Element Compliance Review, part 1 | Alternate milestone selected for 2019 ( * )
|
|
Complete Johnson Space Center (JSC) Chamber A decommissioning | 6/14/18 | |
June 2018 | Launch Readiness Exercise #1 | Alternate milestone selected for 2019 ( * )
|
Deliver final version of the spacecraft handbook to NASA | 5/9/18 | |
May 2018 | Begin Spacecraft Element thermal vacuum test | Replanned to 04/2019 |
Deliver analysis of launch effects on JWST Observatory | Replanned to 03/2019 | |
April 2018 | Deliver results from Spacecraft Element acoustic and vibration tests | Replanned to 02/2019 |
Complete post shipment functional testing of the Telescope | Replanned to 01/2019 | |
March 2018 | Complete Spacecraft Element vibration test | Replanned to 11/2018 |
Spacecraft thrusters modules ready for installation | 2/19/18 | |
Ship telescope from NASA/JSC to Northrop Grumman | 2/2/18 | |
February 2018 | Complete Spacecraft Element (combined spacecraft and sunshield) Acoustic Test | Started 3/25/2018 |
Conduct Observatory Deployment Review #3 | 1/31/18 | |
January 2018 | Complete Wavefront Sensing & Control commissioning exercise | 3/10/2018 |
Install spacecraft horizontal radiator panels | 1/3/18 |
2017:
show/hide
2016:
show/hide
2015:
show/hide
2014:
show/hide
2013:
show/hide
2012:
show/hide
2011:
show/hide